Continuity Tests
Remove power mirror switch. See POWER MIRROR SWITCH under REMOVAL & INSTALLATION. Using an ohmmeter, check for continuity between appropriate mirror switch terminals. See Fig 1. See POWER MIRROR SWITCH CONTINUITY TEST table. If switch fails any test, replace switch.
POWER MIRROR SWITCH CONTINUITY TEST
| Application Type | Continuity Should Exist Between Terminals No. | |||
|---|---|---|---|---|
| L/R Switch In OFF Position | ||||
| UP Or LEFT (1) | 7 & 8 | |||
| DOWN Or RIGHT (1) | 3 & 7 | |||
| L/R Switch In LEFT Position | ||||
| UP (1) | 3 & 6, 7 & 8 | |||
| DOWN (1) | 3 & 7, 6 & 8 | |||
| LEFT (1) | 2 & 3, 7 & 8 | |||
| RIGHT (1) | 2 & 8, 3 & 7 | |||
| L/R Switch In RIGHT Position | ||||
| UP (1) | 3 & 5, 7 & 8 | |||
| DOWN (1) | 3 & 7, 5 & 8 | |||
| LEFT (1) | 1 & 3, 7 & 8 | |||
| RIGHT (1) | 1 & 8, 3 & 7 | |||
|
||||