Park/Neutral Position Switch: Installation
- INSTALL PARK/NEUTRAL POSITION SWITCH ASSEMBLY
- Install the switch to the manual valve shaft.
- Temporarily install the bolt.
- Install a new lock washer with the nut.
Torque: 6.9 N*m (70 kgf*cm, 61 in.*lbf)
- Temporarily install the control shaft lever.
- Turn the control shaft lever counterclockwise until it stops, and then turn it clockwise 2 notches to set it to the N position.
- Remove the control shaft lever.
- Align the neutral basic line with the groove.
- Hold the switch in position and tighten the bolt.
Torque: 13 N*m (130 kgf*cm, 9 ft.*lbf)
- Using a screwdriver, bend the tabs of the lock washer.
HINT:
Bend at least 2 washer tabs.
- Install the transmission control shaft lever and spring washer with the nut.
Torque: 16 N*m (160 kgf*cm, 12 ft.*lbf)
- Connect the switch connector.
- CONNECT FLOOR SHIFT GEAR SHIFTING ROD SUB-ASSEMBLY
- Temporarily connect the shifting rod to the connecting rod swivel with the nut.
HINT:
The nut is tightened to a torque specification during the shift lever position adjustment procedure.
- Temporarily connect the shifting rod to the connecting rod swivel with the nut.
- ADJUST SHIFT LEVER POSITION
- Adjust the shift lever position (See ADJUSTMENT ).
- INSTALL FRONT FLOOR NO. 1 HEAT INSULATOR (See INSTALLATION )
- INSTALL FRONT EXHAUST PIPE ASSEMBLY
- Install the front exhaust pipe (See INSTALLATION ).
- CONNECT CABLE TO NEGATIVE BATTERY TERMINAL NOTE: When disconnecting the cable, some systems need to be initialized after the cable is reconnected (See INITIALIZATION ).
- INSTALL COWL TOP VENTILATOR LOUVER (See INSTALLATION )
- INSPECT PARK/NEUTRAL POSITION SWITCH ASSEMBLY
- Inspect the switch (See ON-VEHICLE INSPECTION ).