Installation [08/2015 - ]: Procedure
- INSTALL NO. 2 AIR TUBE GASKET
- Install a new No. 2 air tube gasket to the intercooler assembly with the protrusion of the No. 2 air tube gasket oriented as shown in the illustration.
*a Protrusion NOTE:Install a new No. 2 air tube gasket to the intercooler assembly with the protrusion of the No. 2 air tube gasket oriented as shown in the illustration.
- Install a new No. 2 air tube gasket to the intercooler assembly with the protrusion of the No. 2 air tube gasket oriented as shown in the illustration.
- INSTALL THROTTLE BODY GASKET
- Install a new throttle body gasket to the No. 2 air tube with the protrusion of the throttle body gasket oriented as shown in the illustration.
*a Protrusion NOTE:Install a new throttle body gasket to the intercooler assembly with the protrusion of the throttle body gasket oriented as shown in the illustration.
- Install a new throttle body gasket to the intake manifold with the protrusion of the throttle body gasket oriented as shown in the illustration.
*a Protrusion NOTE:Install a new throttle body gasket to the intercooler assembly with the protrusion of the throttle body gasket oriented as shown in the illustration.
- Install a new throttle body gasket to the No. 2 air tube with the protrusion of the throttle body gasket oriented as shown in the illustration.
- INSTALL THROTTLE BODY WITH MOTOR ASSEMBLY
HINT:
Perform "Inspection After Repair" after replacing the throttle body with motor assembly.
Refer to INITIALIZATION [08/2015 - 09/2018] , or refer to INITIALIZATION [09/2018 - 09/2019] , or refer to INITIALIZATION [09/2019 - ]
- Install the throttle body with motor assembly and No. 2 air tube to the intake manifold with the 4 bolts.
Torque: 10 N.m (102 kgf/cm, 7 ft.lbf)
- Temporarily install the No. 2 air tube to the intercooler assembly with the 4 bolts.
Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
HINT:
Temporarily install the bolts in the order shown in the illustration.
- Tighten the 4 bolts.
HINT:
Tighten the bolts in the order shown in the illustration.
Torque: 10 N.m (102 kgf/cm, 7 ft.lbf)
- Connect the No. 2 water by-pass hose and No. 1 water by-pass hose to the throttle body with motor assembly and slide the 2 hose clamps to secure them.
- Connect the throttle body with motor assembly connector.
- Install the 2 bolts to connect the No. 6 water by-pass pipe to the intercooler assembly and No. 2 air tube.
Torque: 10 N.m (102 kgf/cm, 7 ft.lbf)
- Engage the 2 engine wire clamps.
- Connect the engine wire connector.
- Connect the injector connector (for Direct Injection).
- Install the throttle body with motor assembly and No. 2 air tube to the intake manifold with the 4 bolts.
- ADD ENGINE COOLANT
Refer to PROCEDURE - Step 3
- INSPECT FOR COOLANT LEAK
Refer to PROCEDURE - Step 1
- PERFORM INITIALIZATION NOTE:
- Be sure to perform this procedure after removing and reinstalling the throttle body with motor assembly or any throttle body with motor assembly components.
- Perform the following procedure after replacing the throttle body with motor assembly or any throttle body with motor assembly components. The following procedure should also be performed if the throttle body with motor assembly is cleaned.
- Connect the GTS to the DLC3.
- Clear the DTCs.
Refer to DTC CHECK / CLEAR [08/2015 - ]
- Perform "Inspection After Repair".
Refer to INITIALIZATION [08/2015 - 09/2018] , or refer to INITIALIZATION [09/2018 - 09/2019] , or refer to INITIALIZATION [09/2019 - ]
- Start the engine and check that the MIL is not illuminated. After the engine is warmed up, check that the idle speed is within the specified range with the A/C switch off.
Standard
750 to 850 rpm
NOTE:- Be sure to perform this step with all accessories off.
- Make sure that the shift lever is in N or P.
- Enter the following menus: Powertrain / Engine / Data List / Throttle Sensor Position.
Powertrain > Engine > Data List
Tester Display Throttle Sensor Position - Fully depress the accelerator pedal and check that the value of Throttle Sensor Position is 60% or higher.
- Perform a road test and confirm that there are no abnormalities.
- INSTALL ENGINE UNDER COVER
Refer to PROCEDURE - Step 79 [08/2015 - 10/2016] , or refer to PROCEDURE - Step 78 [10/2016 - 09/2020] , or refer to PROCEDURE - Step 78 [09/2020 - ]