Installation [10/2015 - ]: Procedure
- INSTALL SPARK PLUG
HINT:
Perform "Inspection After Repair" after replacing a spark plug.
Refer to INITIALIZATION [10/2015 - ]
- Install the 8 spark plugs to the cylinder head sub-assembly and cylinder head LH.
Torque: 21 N*m (214 kgf*cm, 15 ft.*lbf)
NOTE:If a spark plug has been struck or dropped, replace it.
HINT:
Install the same parts to their original positions.
- Install the 8 spark plugs to the cylinder head sub-assembly and cylinder head LH.
- INSTALL IGNITION COIL ASSEMBLY
Refer to PROCEDURE - Step 2
- INSTALL NO. 3 ENGINE ROOM RELAY BLOCK ASSEMBLY
Refer to PROCEDURE - Step 4
- INSTALL NO. 1 ENGINE ROOM RELAY BLOCK ASSEMBLY
Refer to PROCEDURE - Step 5
- INSTALL BATTERY TRAY
Refer to PROCEDURE - Step 6
- INSTALL POWER STEERING ECU ASSEMBLY
Refer to INSTALLATION [10/2015 - ]
- INSTALL V-BANK COVER SUB-ASSEMBLY
Refer to PROCEDURE - Step 2 [10/2015 - 09/2017] or refer to PROCEDURE - Step 2 [09/2017 - 05/2018] or refer to PROCEDURE - Step 2 [05/2018 - ]
- CONNECT CABLE TO NEGATIVE BATTERY TERMINAL
See step 2
NOTE:When disconnecting the cable, some systems need to be initialized after the cable is reconnected.
Refer to INITIALIZATION [10/2015 - 09/2016] or refer to INITIALIZATION [09/2016 - 09/2017] or refer to INITIALIZATION [09/2017 - ]
- PERFORM INITIALIZATION
- Perform "Inspection After Repair" after replacing an ignition coil assembly and spark plug.
Refer to INITIALIZATION [10/2015 - ]
- Perform "Inspection After Repair" after replacing an ignition coil assembly and spark plug.