Installation [03/2017 - ]: Procedure

  1. INSTALL MASS AIR FLOW METER SUB-ASSEMBLY 

    HINT: 

    Perform "Inspection After Repair" after replacing the mass air flow meter sub-assembly.

    Refer to INITIALIZATION [03/2017 - ]

    1. for Bank 2:
      1. Install the mass air flow meter sub-assembly with the 2 screws.
        NOTE:
        • If the mass air flow meter sub-assembly has been struck or dropped, replace it.
        • If reusing the mass air flow meter sub-assembly, be sure to inspect the O-ring.
        • Make sure that the O-ring is not cracked or does not move out of place during installation.
    2. for Bank 1:
      1. Install the mass air flow meter sub-assembly with the 2 screws.
      2. Connect the mass air flow meter sub-assembly connector.
        NOTE:
        • If the mass air flow meter sub-assembly has been struck or dropped, replace it.
        • If reusing the mass air flow meter sub-assembly, be sure to inspect the O-ring.
        • Make sure that the O-ring is not cracked or does not move out of place during installation.
  2. INSTALL AIR CLEANER WITH ELEMENT ASSEMBLY RH 

    Refer to PROCEDURE - Step 96 [03/2017 - 06/2019] , or refer to PROCEDURE - Step 96 [06/2019 - 05/2023] , or refer to PROCEDURE - Step 100 [05/2023 - 09/2023] , or refer to PROCEDURE - Step 102 [09/2023 - ]

  3. INSTALL RADIATOR SUPPORT TO CROSS MEMBER BRACE SUB-ASSEMBLY RH 

    Refer to PROCEDURE - Step 14 [03/2017 - 04/2020] , or refer to PROCEDURE - Step 14 [04/2020 - 05/2023] , or refer to PROCEDURE - Step 15 [05/2023 - 09/2023] , or refer to PROCEDURE - Step 15 [09/2023 - ]

  4. INSTALL LOWER RADIATOR AIR DEFLECTOR 

    Refer to PROCEDURE - Step 8 [03/2017 - 05/2023] , or refer to PROCEDURE - Step 8 [05/2023 - ]

  5. INSTALL RADIATOR SUPPORT TO FRAME SEAL LH 

    Refer to PROCEDURE - Step 9 [03/2017 - 05/2023] , or refer to PROCEDURE - Step 9 [05/2023 - ]

  6. INSTALL RADIATOR SUPPORT TO FRAME SEAL RH 

    Refer to PROCEDURE - Step 10 [03/2017 - 05/2023] , or refer to PROCEDURE - Step 10 [05/2023 - ]

  7. INSTALL V-BANK COVER SUB-ASSEMBLY 

    Refer to PROCEDURE - Step 138 [03/2017 - 06/2019] , or refer to PROCEDURE - Step 138 [06/2019 - 05/2023] , or refer to PROCEDURE - Step 141 [05/2023 - 09/2023] , or refer to PROCEDURE - Step 147 [09/2023 - ]