Installation [01/2017 - 05/2023]: Procedure
- INSTALL FRONT STEERING CONTROL ECU
- Install the front steering control ECU with the 2 nuts.
Torque: 5.5 N*m (56 kgf*cm, 49 in.*lbf)
- Connect the 4 connectors to the front steering control ECU.
- Return the floor carpet to its original position.
- Install the front steering control ECU with the 2 nuts.
- INSTALL GLOVE COMPARTMENT DOOR ASSEMBLY
Refer to PROCEDURE - Step 15 [01/2017 - 06/2019] , or refer to PROCEDURE - Step 15 [06/2019 - 04/2020] , or refer to PROCEDURE - Step 15 [04/2020 - 05/2023]
- INSTALL NO. 2 INSTRUMENT PANEL GARNISH SUB-ASSEMBLY
Refer to PROCEDURE - Step 27 [01/2017 - 06/2019] , or refer to PROCEDURE - Step 27 [06/2019 - 04/2020] , or refer to PROCEDURE - Step 27 [04/2020 - 05/2023]
- INSTALL LOWER NO. 2 INSTRUMENT PANEL AIRBAG ASSEMBLY
Refer to INSTALLATION [01/2017 - 05/2023]
- CONNECT CABLE TO NEGATIVE AUXILIARY BATTERY TERMINAL
Refer to PROCEDURE - Step 2
NOTE:When disconnecting the cable, some systems need to be initialized after the cable is reconnected.
Refer to INITIALIZATION [01/2017 - 04/2020] , or refer to INITIALIZATION [04/2020 - 05/2023]
- INSTALL NO. 2 DECK BOARD
Refer to PROCEDURE - Step 13 [01/2017 - 01/2021] , or refer to PROCEDURE - Step 13 [01/2021 - 05/2023]
- PERFORM VARIABLE GEAR RATIO STEERING SYSTEM CALIBRATION
Refer to CALIBRATION [01/2017 - ]