Installation [09/2014 - ]: Procedure
- INSTALL TRANSMISSION FLOOR SHIFT ASSEMBLY
- Temporarily install the transmission floor shift assembly to the vehicle body with the 4 bolts.NOTE:
Do not pinch the wire harness.
- Fully tighten the 4 bolts in the order shown in the illustration to install the transmission floor shift assembly.
Torque: 8.3 N.m (85 kgf/cm, 73 in.lbf)
- Connect the transmission control switch connector.NOTE:
Be sure to securely connect the transmission control switch connector.
- Engage the 4 clamps to connect the wire harness to the transmission floor shift assembly.
- Connect the shift lock control ECU connector.NOTE:
Be sure to securely connect the shift lock control ECU connector.
- Temporarily install the transmission floor shift assembly to the vehicle body with the 4 bolts.
- INSTALL NO. 1 CONSOLE BOX DUCT
- Install the No. 1 console box duct with the 2 clips.
- Engage the clamp to connect the wire harness to the No. 1 console box duct.
- INSTALL CONSOLE BOX ASSEMBLY
Refer to INSTALLATION [09/2014 - 03/2019] , or refer to INSTALLATION [03/2019 - ]
- INSTALL FLOOR SHIFT GEAR SHIFTING ROD SUB-ASSEMBLY
- Turn the transmission control shaft lever RH counterclockwise until it stops, then turn it clockwise 2 notches.
*1 Transmission Control Shaft Lever RH *a P *b R *c N - Move the shift lever to N.
- Connect the floor shift gear shifting rod sub-assembly to the lever of the transmission floor shift assembly.
*a Lever Rear of the vehicle - Temporarily install the nut to the lever of the transmission floor shift assembly.
- Tighten the nut while lightly pushing the lever of the transmission floor shift assembly toward the rear of the vehicle.
Torque: 12.8 N.m (131 kgf/cm, 9 ft.lbf)
NOTE:Do not push the lever of the transmission floor shift assembly too hard.
- Turn the transmission control shaft lever RH counterclockwise until it stops, then turn it clockwise 2 notches.
- INSTALL FRONT NO. 1 FLOOR HEAT INSULATOR
Refer to PROCEDURE - Step 5 [09/2014 - 01/2023] , or refer to PROCEDURE - Step 5 [01/2023 - ]
- INSTALL FRONT EXHAUST PIPE ASSEMBLY (TWC: Rear Catalyst)
Refer to INSTALLATION [09/2014 - 10/2015] , or refer to INSTALLATION [10/2015 - 03/2019] , or refer to INSTALLATION [03/2019 - ]
- INSTALL SHIFT LEVER CAP
- INSPECT SHIFT LEVER POSITION
See step 1
- INSPECT FOR EXHAUST GAS LEAK
Refer to PROCEDURE - Step 9 [09/2014 - 10/2015] , or refer to PROCEDURE - Step 9 [10/2015 - 03/2019] , or refer to PROCEDURE - Step 9 [03/2019 - ]