Installation [08/2020 - ]: Procedure
- INSTALL FRONT ENGINE MOUNTING INSULATOR
- Install the stay to the front engine mounting insulator with the nut.
Torque: 6.0 N.m (61 kgf/cm, 53 in.lbf)
- Install the front engine mounting insulator to the front frame assembly with the 3 nuts.
Torque: 72 N.m (734 kgf/cm, 53 ft.lbf)
- Install the front engine mounting bracket to the transaxle housing with the 3 bolts.
Bolt (A), (B) and (C)
Torque: 42 N.m (428 kgf/cm, 31 ft.lbf)
NOTE:Temporarily tighten the bolt (A), and then fully tighten the 3 bolts in the order of (B), (C) and (A).
- Install the front engine mounting bracket to the front engine mounting insulator with the bolt.
Bolt (D)
Torque: 72 N.m (734 kgf/cm, 53 ft.lbf)
- Install the vacuum hose to the front engine mounting insulator.
- Engage the 2 clamps to install the vacuum hoses to the front engine mounting insulator.
- Install the No. 1 radiator bracket to the front engine mounting bracket with the bolt.
Torque: 19 N.m (194 kgf/cm, 14 ft.lbf)
- Engage the 4 clamps to install the radiator hose, vacuum hoses and No. 2 engine wire to the No. 1 radiator bracket.
- Install the stay to the front engine mounting insulator with the nut.
- INSTALL SUSPENSION TOWER DAMPER (w/ Performance Damper)
Refer to PROCEDURE - Step 1
- INSTALL NO. 2 ENGINE UNDER COVER ASSEMBLY
Refer to PROCEDURE - Step 71 [08/2020 - 08/2021] , or refer to PROCEDURE - Step 72 [08/2021 - ]
- INSTALL NO. 1 ENGINE UNDER COVER
Refer to PROCEDURE - Step 72 [08/2020 - 08/2021] , or refer to PROCEDURE - Step 73 [08/2021 - ]
- INSTALL FRONT WHEEL OPENING EXTENSION PAD LH
Refer to PROCEDURE - Step 73 [08/2020 - 08/2021] , or refer to PROCEDURE - Step 74 [08/2021 - ]
- INSTALL FRONT WHEEL OPENING EXTENSION PAD RH
Refer to PROCEDURE - Step 74 [08/2020 - 08/2021] , or refer to PROCEDURE - Step 75 [08/2021 - ]
- INSTALL VACUUM SWITCHING VALVE (for Active Control Engine Mount System)
Refer to INSTALLATION [08/2020 - ]