Circuit/System Testing
PNP Switch Malfunction (MYC 6L80E, MYD 6L90E)
- Inspect the range selector lever cable for proper adjustment. Refer to Range Selector Lever Cable Adjustment .
- Ignition OFF. Disconnect the 16-way harness connector from the transmission.
- Ignition ON. Measure voltage on the park/neutral signal circuit terminal 3 with a DMM. Verify that there is greater than 10 V on the park/neutral signal circuit.
- If there is less than 10 V on the park/neutral signal circuit, test the circuit for an open or a short to ground. If OK, replace the ECM.
- Ignition OFF, reconnect the 16-way harness connector to the transmission.
- Remove the automatic transmission fluid pan. Refer to Automatic Transmission Fluid, Fluid Pan and/or Filter Replacement .
- Disconnect the manual shift shaft position switch connector at the control solenoid valve assembly. Refer to Manual Shift Shaft Position Switch Replacement .
- Ignition ON, verify that the scan tool PNP Switch parameter displays In Gear.
- If not the specified value, replace the ECM.
- Connect a 3 A fused jumper wire between the park/neutral signal terminal F at the control solenoid valve assembly and ground. The scan tool PNP Switch parameter should display Park/Neutral when the terminal is connected to ground.
- If not the specified value, replace the ECM.
- If all components test normal, test or replace the manual shift shaft position switch.
STRTR Relay Malfunction
- Ignition OFF, disconnect the STRTR relay.
- Ignition ON, transmission in Park/Neutral. Verify that a test lamp illuminates between the relay coil ground circuit terminal and B+.
- If the test lamp does not illuminate, test the ground circuit for an open/high resistance.
- Probe the STRTR Relay switch B+ circuit terminal with a test lamp that is connected to ground. Verify that the test lamp illuminates.
- If the test lamp does not illuminate, test the B+ circuit for a short to ground or an open/high resistance. If the circuit tests normal and the STRTR fuse is open, test the relay controlled output circuit for a short to ground.
- Connect a test lamp between the relay coil ground circuit terminal and the relay coil control circuit terminal.
- Ignition ON, transmission in Park/Neutral. Command the Starter Relay ON and OFF with a scan tool, or turn the ignition switch between the START and RUN positions. The test lamp should turn ON and OFF when changing between the commanded states.
- If the test lamp is always ON, test the relay coil control circuit for a short to voltage. If the circuit tests normal, replace the ECM.
- If the test lamp is always OFF, test the relay coil control circuit for a short to ground or and open/high resistance. If the circuit tests normal, replace the ECM.
- Connect the START relay.
- Install a test lamp between the starter terminal S X2 and ground.
- Ignition ON, transmission in Park/Neutral, command the Starter Relay ON with a scan tool, or turn the ignition switch to the START position. The test lamp should illuminate.
- If the test lamp does not illuminate, test the relay controlled output circuit for an open/high resistance. If the circuit tests normal, test or replace the STRTR relay.
- If all circuits test normal, test or replace the starter.
NOTE:
The engine may begin to crank.
NOTE:
The engine may begin to crank.