Installation Procedure

  1. Install the relay rod to the vehicle.
  2. Install the relay rod to the pitman arm and idler arm.
    Fig 1: Idler Arm To Relay Rod Retaining Nut
    GM828852Courtesy of GENERAL MOTORS CORP.
  3. NOTE: Refer to Fastener Notice in Cautions and Notices.
  4. Install the new relay rod to the idler arm retaining nut.

    Tighten:  Tighten the nut to 63 N.m (47 lb ft).

  5. Fig 2: Locating Pitman Arm
    GM828839Courtesy of GENERAL MOTORS CORP.
  6. Install the new relay rod to the pitman arm retaining nut.

    Tighten:  Tighten the nut to 63 N.m (47 lb ft).

  7. Fig 3: Removed Inner Tie Rods
    GM837714Courtesy of GENERAL MOTORS CORP.
  8. Install the inner tie rods to the relay rod.
  9. Fig 4: Inner Tie Rod To Relay Rod Retaining Nut
    GM832413Courtesy of GENERAL MOTORS CORP.
  10. Install the inner tie rods to relay rod retaining nuts.
  11. Fig 5: Tightening Inner Tie Rod To Relay Rod Retaining Nut
    GM858410Courtesy of GENERAL MOTORS CORP.
  12. Tighten the inner tie rods to relay rod retaining nuts using J 34028  .

    Tighten:  Tighten the nuts to 112 N.m (83 lb ft).

  13. Lower the vehicle.
  14. Verify the wheel alignment. Refer to Measuring Wheel Alignment in Wheel Alignment.