Power Circuits

Turn ignition on. Check for battery voltage on ECU terminals No. 102 and 107. If battery voltage is not present, check operation of MPI control relay. See RELAYS  under MOTORS, RELAYS & SOLENOIDS.

ENGINE CONTROL UNIT (ECU) LOCATION

Application Location
Colt Vista Under driver's seat
All Others Near right kick panel