Diagnostic Test
- CHECK IF DTC IS CURRENT
- CHECK THE (T118) BANK 2 SOLENOID POWER CIRCUIT FOR AN OPEN
- Turn the ignition off to the lock position.
- Disconnect the Transmission C1 harness connectors.
- Disconnect the TCM C1 harness connector.
- Measure the resistance of the (T118) Bank 2 Solenoid Power circuit between the Transmission C1 harness connector and the TCM C1 harness connector.
Is the resistance below 5.0 Ohms?
Yes
- Go To 3
No
- Repair the (T118) Bank 2 Solenoid Power circuit for an open.
- Perform TRANSMISSION VERIFICATION TEST. Refer to 6F24 TRANSMISSION VERIFICATION TEST .
- CHECK THE (T803) PRESSURE CONTROL SOLENOID A (1) CONTROL CIRCUIT FOR AN OPEN
- Measure the resistance of the (T803) Pressure Control Solenoid A (1) Control circuit between the Transmission C1 harness connector and the TCM C1 harness connector.
Is the resistance below 5.0 Ohms?
Yes
- Go To 4
No
- Repair the (T803) Pressure Control Solenoid A (1) Control circuit for an open.
- Perform TRANSMISSION VERIFICATION TEST. Refer to 6F24 TRANSMISSION VERIFICATION TEST .
- Measure the resistance of the (T803) Pressure Control Solenoid A (1) Control circuit between the Transmission C1 harness connector and the TCM C1 harness connector.
- CHECK THE PRESSURE CONTROL SOLENOID A (1)
- Turn the ignition off to the lock position.
- Measure the resistance of the Pressure Control Solenoid A (1) between the appropriate terminals at the Transmission C1 harness connector.
Is the resistance of the Pressure Control Solenoid A (1) 5.1 Ohms (± 0.3 Ohm) at 25° C (77° F)?
Yes
- Using the schematics as a guide, check the Transmission Control Module (TCM) pins, terminals, and connectors for corrosion, damage, or terminal push out. Pay particular attention to all power and ground circuits. If no problems are found, replace and program the TCM in accordance with the Service Information. Refer to REMOVAL .
- Perform TRANSMISSION VERIFICATION TEST. Refer to 6F24 TRANSMISSION VERIFICATION TEST .
No
- Remove the transmission side cover and inspect the internal lead frame. If there are no problems found with the lead frame, replace the Pressure Control Solenoid A (1) in accordance with the Service Information.
- Perform TRANSMISSION VERIFICATION TEST. Refer to 6F24 TRANSMISSION VERIFICATION TEST .
- CHECK WIRING AND CONNECTORS
- The conditions necessary to set the DTC are not present at this time.
- Using the schematics as a guide, inspect the wiring and connectors specific to this circuit.
- Wiggle the wires while checking for shorted and open circuits.
- Check for any Service Bulletins that may apply.
Were there any problems found?
Yes
- Repair as necessary.
- Perform TRANSMISSION VERIFICATION TEST. Refer to 6F24 TRANSMISSION VERIFICATION TEST .
No
- Test Complete.