Home >> Dodge and Ram >> 2013 >> Dart R/T, Automatic Trans >> Repair and Diagnosis >> Transmission >> Transmission Control Systems >> (Transmission Control Module (TCM) - Electrical Diagnostics - 6F24 Automatic Transmission) >> DTC Troubleshooting >> P0963-Pressure Control Solenoid 1 Control Circuit High >> Diagnostic Test
April 5, 2026: LEMON Manuals is launched! Read the announcement.

Diagnostic Test

  1. CHECK IF DTC IS CURRENT 
    1. Using the scan tool, read TCM DTCs.
    2. Record the Environmental Data and any DTCs.
    3. Clear DTCs.
    4. Using the recorded Environmental Data, along with the When Monitored and Set Conditions above, operate the vehicle in the conditions that set the DTC.
    5. Read TCM DTCs.

      Did the DTC reset?

      Yes 

      • Go To  2

      No 

      • Go To  5
  2. CHECK THE (T118) BANK 2 SOLENOID POWER CIRCUIT FOR A SHORT TO VOLTAGE 
    1. Turn the ignition off to the lock position.
    2. Disconnect the Transmission C1 harness connectors.
    3. Disconnect the TCM C1 harness connector.
    4. Turn the ignition on.
    5. Measure the voltage of the (T118) Bank 2 Solenoid Power circuit between ground and the Transmission C1 harness connector.

      Is the voltage above 0.5 of a volt?

      Yes 

      No 

      • Go To  3
  3. CHECK THE (T803) PRESSURE CONTROL SOLENOID A (1) CONTROL CIRCUIT FOR A SHORT TO VOLTAGE 
    1. Measure the voltage of the (T803) Pressure Control Solenoid A (1) Control circuit between ground and the Transmission C1 harness connector.

      Is the voltage above 0.5 of a volt?

      Yes 

      • Repair the (T803) Pressure Control Solenoid A (1) Control circuit for a short to voltage.
      • Perform the TRANSMISSION VERIFICATION TEST. Refer to 6F24 TRANSMISSION VERIFICATION TEST  .

      No 

      • Go To  4
  4. CHECK THE PRESSURE CONTROL SOLENOID A (1) 
    1. Turn the ignition off to the lock position.
    2. Measure the resistance of the Pressure Control Solenoid A (1) between the appropriate terminals of the Transmission C1 harness connector.

      Is the resistance of the Pressure Control Solenoid A (1) 5.1 Ohms (± 0.3 Ohm) at 25° C (77° F)?

      Yes 

      • Using the schematics as a guide, check the Transmission Control Module (TCM) pins, terminals, and connectors for corrosion, damage, or terminal push out. Pay particular attention to all power and ground circuits. If no problems are found, replace and program the TCM in accordance with the Service Information. Refer to REMOVAL .
      • Perform the TRANSMISSION VERIFICATION TEST. Refer to 6F24 TRANSMISSION VERIFICATION TEST  .

      No 

      • Remove the transmission side cover and inspect the internal lead frame. If there are no problems found with the lead frame, replace the Pressure Control Solenoid A (1) in accordance with the Service Information.
      • Perform the TRANSMISSION VERIFICATION TEST. Refer to 6F24 TRANSMISSION VERIFICATION TEST  .
  5. CHECK WIRING AND CONNECTORS 
    1. The conditions necessary to set the DTC are not present at this time.
    2. Using the schematics as a guide, inspect the wiring and connectors specific to this circuit.
    3. Wiggle the wires while checking for shorted and open circuits.
    4. Check for any Service Bulletins that may apply.

      Were there any problems found?

      Yes 

      No 

      • Test Complete.