Retainer, Battery: Installation

GC0079993Courtesy of CHRYSLER GROUP, LLC
  1. Install the battery holddown clamp and bolt. Tighten the bolt to the proper torque specifications. Refer to TORQUE SPECIFICATIONS .
  2. Connect the negative battery cable to the Intelligent Battery Sensor (IBS) M8 stud and tighten to the proper torque specifications. Refer to TORQUE SPECIFICATIONS .
  3. Install the rear compartment floor trim panel.