Component Inspection
- OCV Inspection
- IG "OFF" & Disconnect OCV connector.
- Measure resistance between terminal 1 and 2 of OCV connector (Component Side)
SPECIFICATION
SPECIFICATIONResistance (Ω) 6.7 ~ 7.7 - Is the measured resistance within specification?
YES
- Go to " 2Check CAM PHASER with actuation test" as follow.
NO
- Substitute with a known - good OCV and check for proper operation. If the problem is corrected, replace OCV and go to "VERIFICATION OF VEHICLE REPAIR " procedure.
- Check CAM PHASER with actuation test
- Connect scantool and IG "ON"
- Select "CAM PHASER INTAKE BANK 1" on the Actuation Test
- Select "OIL CONTROL VALVE" on the Actuation Test
- Activates "CAM PHASER INTAKE BANK 1" by pressing "STRT (F1)" key
- Activates "OIL CONTROL VALVE" by pressing "STRT (F1)" key
- Repeat this procedure 4 or 5 times to ensure CAM PHASER and intake valve control solenoid reliability
- Has a problem been found ?
YES
- Substitute with a known - good CVVT or OCV and check for proper operation.
If the problem is corrected, replace CVVT or OCV and go to "VERIFICATION OF VEHICLE REPAIR " procedure.
NO
- Fault is intermittent. Drive the vehicle to meet the enable condition for the DTC. and Go to "VERIFICATION OF VEHICLE REPAIR " procedure