Tilt Steering Column: Reassembly

NOTE: When using a vise, do not overtighten it.
  1. COAT PARTS INDICATED BY ARROWS WITH MOLYBDENUM DISULFIDE LITHIUM BASE GREASE 

    (See  TILT STEERING COLUMN  ) 

  2. INSTALL MAIN SHAFT BUSHING 
    1. Coat a new main shaft bushing with molybdenum disulfide lithium base grease.
    2. Using SST and a hammer, tap in the main shaft bushing.

      SST 09612-22011

      Fig 1: Installing Main Shaft Bearing
      G01180697Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
  3. INSTALL COMPRESSION SPRING, BEARING THRUST COLLAR AND BEARING 
  4. INSTALL UPPER COLUMN TUBE SUB-ASSEMBLY TO MAIN SHAFT ASSEMBLY 
    1. Temporarily install the upper column tube sub-assembly to the No. 1 main shaft.
    2. Secure the No. 1 main shaft with upper column tube sub-assembly and SST in a vise.

      SST 09316-60011 (09316-00051)

      Fig 2: Secure Main Shaft With Upper Column Tube Sub-Assembly And SST In A Vise
      G01180698Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
    3. Using SST, compress the spring of the upper column tube sub-assembly.

      SST 09950-40011 (09951-04010, 09952-04010, 09953-04020, 09954-04010, 09955-04061, 09958-04011)

      NOTE: Do not overtighten the SST.
    4. Using a snap ring expander, install a new snap ring and No. 1 main shaft.
      Fig 3: Using SST, Compress Spring Of Upper Column Tube Sub-Assembly
      G01180699Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
    5. Assemble the No. 1 main shaft with upper column tube sub-assembly and No. 2 main shaft sub-assembly.
    NOTE: Do not bend the universal joint of the shaft more than 20°.
    Fig 4: Identifying No. 1 Main Shaft With Upper Column Tube Sub-Assembly And No. 2 Main Shaft Sub-Assembly
    G01180700Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
  5. INSTALL MAIN SHAFT ASSEMBLY WITH UPPER COLUMN TUBE SUB-ASSEMBLY 
    1. Using a pin punch (5 mm) and a hammer, install the pawl assembly with a new No. 2 tilt steering shaft.
      Fig 5: Installing Pawl Assembly
      G01180701Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002

      HINT:

      Install a new No. 2 tilt steering shaft with the one having the mark corresponding to the mark stamped on the pawl assembly.

      Fig 6: Identifying Stamp Mark On Pawl Assembly
      G01180703Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
      Fig 7: Pawl Assembly And No. 2 Tilt Shaft Part Number Chart
      G01180702Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
    2. Install the main shaft assembly with the upper column tube sub-assembly and pawl retainer.
    3. Using a hexagon wrench (6 mm), install the 2 tilt steering shafts.

      Torque: 20 N.m (210 kgf.cm, 15 ft.lbf) 

    Fig 8: Installing Tilt Steering Shafts
    G01180704Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
  6. INSTALL TILT LEVER ASSEMBLY 
    1. Install the 2 bushings to the upper column tube sub-assembly.
    2. Install the tilt lever assembly with a new spring nut.
      NOTE: Make sure that the spring nut is installed facing in the correct direction.
    3. Install the tilt lever link.
      Fig 9: Install Tilt Lever Assembly
      G01180705Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
    4. Install the tension spring.
    NOTE: Make sure that the tension spring is installed facing in the correct direction.
  7. INSTALL TURN SIGNAL BRACKET 
    1. Install the turn signal bracket with the 2 bolts.

      Torque: 2.9 N.m (30 kgf.cm, 26 in.lbf) 

      Fig 10: Installing Tension Spring
      G01180706Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
    2. Using pliers, install the tension spring.
    NOTE: Make sure that the tension spring is installed facing in the correct direction.
    Fig 11: Installing Tension Spring
    G01180707Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
  8. INSTALL 2 TENSION SPRINGS 

    Using SST, install the 2 tension springs.

    SST 09703-30010

    Fig 12: Installing 2 Tension Springs Using SST Tools
    G01180708Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
  9. INSTALL COLUMN PROTECTOR 

    Install the column protector with the 2 bolts.

    Torque: 6.1 N.m (60 kgf.cm, 52 in.lbf) 

  10. INSTALL 2 ENERGY ABSORBING PLATES 
    1. Install the 2 new energy absorbing plate guides and energy absorbing plates.
    2. Install the 2 new energy absorbing clips.
      Fig 13: Installing Energy Absorbing Plates
      G01180709Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
  11. INSTALL COLUMN TUBE SUPPORT 
    1. Install the lower column tube attachment to the column tube support.
    2. Install the column tube support with the lower column tube attachment with the bolt.

      Torque: 15 N.m (150 kgf.cm, 11 ft.lbf) 

  12. INSTALL COLUMN UPPER BRACKET AND COLUMN UPPER CLAMP 
    1. Install the column upper bracket and column upper clamp with 2 new tapered-head bolts.
    2. Tighten the 2 tapered-head bolts until the bolt heads break off.
    Fig 14: Installing Column Upper Bracket And Column Upper Clamp
    G01180710Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
  13. INSTALL TRANSPONDER KEY COIL AND KEY CYLINDER LAMP ASSEMBLY 

    Install the key cylinder lamp assembly and transponder key coil with the screw.