Dc / Dc Converter: Installation
- INSTALL DC-DC CONVERTER
- Install the converter with the 3 bolts.
Torque: 8.5 N*m (87 kgf*cm, 75 in.*lbf)
- Connect the 2 converter connectors A and B, and securely lock the connectors.
- Install the converter with the 3 bolts.
- INSTALL BATTERY TRAY
- Install the battery tray with the 3 bolts.
Torque: 5.4 N*m (55 kgf*cm, 47 in.*lbf)
- Install the battery tray with the 3 bolts.
- INSTALL BATTERY
- Install the battery.
- Install the battery insulator.
- Install the battery clamp with the 2 nuts.
Torque: 5.4 N*m (55 kgf*cm, 47 in.*lbf)
- Connect the positive (+) battery cable to the battery terminal.
Torque: 5.6 N*m (57 kgf*cm, 50 in.*lbf)
- Connect the negative (-) battery cable to the battery terminal.
Torque: 5.6 N*m (57 kgf*cm, 50 in.*lbf)
- INSTALL COWL TOP VENTILATOR LOUVER RH (See INSTALLATION )
- INSPECT SRS WARNING LIGHT
- Inspect the SRS warning light (see DIAGNOSIS SYSTEM ).
- PERFORM INITIALIZATION
- Perform initialization (see
INITIALIZATION
).NOTE: Certain systems need to be initialized after disconnecting and reconnecting the cable from the negative (-) battery terminal.
- Perform initialization (see
INITIALIZATION
).