Floor Shift Assembly: Installation
- INSTALL FLOOR SHIFT LEVER ASSEMBLY
- Install the floor shift lever assembly with the 6 bolts.
Torque: 8.3 N*m (85 kgf*cm, 73 in.*lbf)
- Connect the connector to the floor shift lever assembly.
- Install the floor shift lever assembly with the 6 bolts.
- INSTALL FLOOR SHIFT GEAR SHIFTING ROD SUB-ASSEMBLY
- Shift into the N position.
- Connect the No. 1 floor shift gear shifting rod and connecting rod swivel with the nut.
Torque: 13 N*m (130 kgf*cm, 9 ft.*lbf)
- INSTALL CONSOLE PANEL SUB-ASSEMBLY UPPER
- Install console panel sub-assembly upper (see INSTALLATION ).
- INSTALL SHIFT LEVER KNOB SUB-ASSEMBLY