Component Inspection

WARNING: This page is about a different car, the 2004 Nissan Titan. However, it is still accessible from the selected car via links, so may be relevant.
  1. Apply 12V direct current between transfer relay 1, 2 terminals 1 and 2.
  2. Check continuity between relay terminals 3 and 5.
    Fig 1: Continuity Chart
    G00728748Courtesy of NISSAN MOTOR CO., U.S.A.
  3. If NG, replace the transfer relay 1 or 2.
Fig 2: Identifying Relay Terminals
G00728749Courtesy of NISSAN MOTOR CO., U.S.A.