  1. PRELIMINARY INSPECTION 

    Perform the preliminary inspection. Refer to Diagnosis Procedure .

    GO TO 2 .

  2. STOP POWER GENERATION VOLTAGE VARIABLE CONTROL SYSTEM 

    Stop the operation of the power generation voltage variable control in either of the following procedures:

    • After selecting "ENGINE" using CONSULT, set the DUTY value of "ALTERNATOR DUTY" to 0 % by selecting "ALTERNATOR DUTY" with "Active Test". Continue "Active Test" until the end of inspection. (When the DUTY value is 0 or 100 %, the normal power generation is performed according to the characteristic of the IC regulator of the generator.)
    • Turn the ignition switch OFF, and disconnect the battery current sensor connector. [However, DTC (P1550 - P1554) of the engine might remain. After finishing the inspection, connect the battery current sensor connector and erase the self-diagnostic results history of the engine using CONSULT.]

    GO TO 3 .

  3. INSPECTION WITH CHARGE WARNING LAMP (IGNITION SWITCH IS TURNED ON) 

    When ignition switch is turned ON.

    Does the charge warning lamp illuminate?

    YES

    GO TO 4 .

    NO

    GO TO 10 .

  4. INSPECTION WITH CHARGE WARNING LAMP (IDLING) 

    Start the engine and run it at idle.

    Does the charge warning lamp turn OFF?

    YES

    GO TO 5 .

    NO

    GO TO 6 .

  5. INSPECTION WITH CHARGE WARNING LAMP (ENGINE AT 2, 500 RPM) 

    Increase and maintain the engine speed at 2, 500 rpm.

    Does the charge warning lamp illuminate?

    YES

    GO TO 8 .

    NO

    Inspection End

  6. "L" TERMINAL CIRCUIT (SHORT) INSPECTION 

    Check terminal "L" circuit for (SHORT). Refer to Diagnosis Procedure .

    Is the inspection result normal?

    YES

    GO TO 7 .

    NO

    Repair as needed.

  7. "S" TERMINAL CIRCUIT INSPECTION 

    Check terminal "S" circuit. Refer to Diagnosis Procedure .

    Is the inspection result normal?

    YES

    GO TO 8 .

    NO

    Repair as needed.

  8. MEASURE "B" TERMINAL VOLTAGE 

    Start engine. With engine running at 2, 500 rpm, measure "B" terminal voltage.

    What voltage does the measurement result show?

    Less than 13.0 V

    GO TO 9 .

    More than 16.0 V

    Replace generator. Refer to Removal and Installation - MRA8DE  or Removal and Installation - MR16DDT .

  9. "B" TERMINAL CIRCUIT INSPECTION 

    Check "B" terminal circuit. Refer to Diagnosis Procedure .

    Is the inspection result normal?

    YES

    Replace generator. Refer to Removal and Installation - MRA8DE  or Removal and Installation - MR16DDT .

    NO

    Repair as needed.

  10. INSPECTION WITH CHARGE WARNING LAMP (IGNITION SWITCH IS ON) 
    1. Disconnect generator connector and apply ground to "L" terminal.
    2. Turn the ignition switch ON.

    Does the charge warning lamp illuminate?

    YES

    Replace generator. Refer to Removal and Installation - MRA8DE  or Removal and Installation - MR16DDT .

    NO

    GO TO 11 .

  11. CHECK "L" TERMINAL CIRCUIT (OPEN) 

    Check "L" terminal circuit (OPEN). Refer to Diagnosis Procedure .