Installation Procedure

    IMPORTANT: Route the positive battery cable the same way as originally installed.
  1. Install the positive battery cable to the vehicle and position accordingly.
  2. Fig 1: Positive Cable
    GM1878823Courtesy of GENERAL MOTORS CORP.
    NOTE: Refer to Fastener Notice .
  3. Install the positive battery cable (1) to the starter solenoid BAT stud.

    Tighten:  Tighten the nut (4) to 15 N.m (11 lb ft).

  4. Lower the vehicle.
  5. Position the fusible link cable to the generator control module.
  6. Fig 2: Fusible Link Nut And Bolt
    GM1998501Courtesy of GENERAL MOTORS CORP.
  7. Install the following components to the generator control module.
    • Fusible link nut (1)
    • Fusible link bolt (2)

      Tighten:  Tighten the nuts and bolts to 10 N.m (89 lb in).

  8. Install the generator control module cover. Refer to Generator Control Module Cover Replacement .
  9. Fig 3: Positive Battery Cable Terminal Nut
    GM1999419Courtesy of GENERAL MOTORS CORP.
  10. Install the positive battery cable to the battery.

    Tighten:  Tighten the nut to 5 N.m (45 lb in).

  11. Fig 4: Electronic Control Module Bracket Retaining Nuts And Bolts
    GM2030262Courtesy of GENERAL MOTORS CORP.
  12. Install the electronic control module bracket retaining nuts (1) and bolts (2).

    Tighten:  Tighten the nuts and bolts to 10 N.m (89 lb in).

  13. Connect the positive battery junction block assembly to the bracket.
  14. Connect the negative battery cable. Refer to Battery Negative Cable Disconnection and Connection (With LAT)  or Battery Negative Cable Disconnection and Connection (Without LAT) .