AT Shift Lock Solenoid and "P" Range Switch: Inspection
CONTROL SYSTEM CHART
| Step | Check | Yes | No |
|---|---|---|---|
| 1 CHECK SHIFT LOCK SOLENOID. Measure the resistance of shift lock solenoid connector terminals. Terminals No. 4 - No. 5: |
Is the resistance 20 - 40 Ω? | Go to step 2 . | Replace the shift lock solenoid and "P" range switch assembly. |
| 2 CHECK SHIFT LOCK SOLENOID. Connect the battery to shift lock solenoid connector terminal, and then operate the solenoid. Terminals No.4 (+) - No.5 (-): |
Does the shift lock solenoid operate normally? | Go to step 3 . | Replace the shift lock solenoid and "P" range switch assembly. |
3 CHECK "P" RANGE SWITCH.
|
Is the resistance less than 1 Ω? | Go to step 4 . | Replace the "P" range switch. |
4 CHECK "P" RANGE SWITCH.
|
Is the resistance 1 MΩ or more? | Normal operation | Replace the "P" range switch. |