Transmission Control Cable: Installation

  1. INSTALL TRANSMISSION CONTROL CABLE ASSEMBLY 
    1. Install the retainer to the grommet.
      NOTE: Fit 4 projections of the grommet into 4 holes of the retainer.
      Fig 1: Identifying Retainer And Grommet
      G05234580Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
    2. Install the control cable assembly with the 2 bolts.

      Torque: 5.0 N*m (51 kgf*cm, 44 in.*lbf) 

      Fig 2: Locating Control Cable Assembly With Bolts
      G05234582Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
    3. Connect the shift cable with the 2 nuts.

      Torque: 5.0 N*m (51 kgf*cm, 44 in.*lbf) 

      Fig 3: Locating Shift Cable With Nuts
      G05194232Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
    4. Connect the shift cable with the 2 clip from the bracket.
    5. Connect the shift cable end of the shift cable with the 2 washer and 2 clip to the transaxle.
      Fig 4: Locating Shift Cable End Of Shift Cable
      G05194231Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
  2. CONNECT FLOOR SHIFT CABLE TRANSMISSION CONTROL SELECT 
    1. Connect the select cable to the shift lever assembly.
      NOTE:
      • The projecting part of the cable outer should face upward when the shift cable is installed.
      • Make sure that after installation the cable outer spring is moved to the place shown in the illustration.
        Fig 5: Connecting Select Cable To Shift Lever Assembly
        G05234568Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
    2. Connect the select cable end with the clip to the shift lever assembly.
    3. Connect the select cable to the clamp.
      Fig 6: Connecting Select Cable End With Clip To Shift Lever Assembly
      G05234564Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
  3. CONNECT FLOOR SHIFT CABLE TRANSMISSION CONTROL SHIFT 
    1. Connect the shift cable to the shift lever assembly.
      NOTE:
      • The projecting part of the cable outer should face upward when the shift cable is installed.
      • Make sure that after installation the cable outer spring is moved to the place shown in the illustration.
        Fig 7: Connecting Shift Cable To Shift Lever Assembly
        G05234570Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
    2. Connect the shift cable end as shown in the illustration.
      Fig 8: Identifying Shift Cable End
      G05234571Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
    3. Install the washer and clip.
    4. Connect the shift cable to the clamp.
  4. INSTALL FRONT FLOOR HEAT INSULATOR NO.1 
    1. Install the heat insulator No. 1 with the 3 nuts.

      Torque: 5.5 N*m (56 kgf*cm, 49 in.*lbf) 

  5. INSTALL EXHAUST PIPE ASSEMBLY 

    HINT:

    (See INSTALLATION )

  6. INSTALL AIR BAG SENSOR ASSEMBLY CENTER (See  ON-VEHICLE INSPECTION  ) 
  7. INSTALL INSTRUMENT PANEL FINISH PANEL LOWER CENTER (See  INSTALLATION  ) 
  8. INSTALL INSTRUMENT PANEL BOX (See  INSTALLATION  ) 
  9. INSTALL INSTRUMENT CLUSTER FINISH PANEL ASSEMBLY CTR (See  INSTALLATION  ) 
  10. INSTALL SHIFT LEVER KNOB SUB-ASSEMBLY 
  11. CONNECT BATTERY NEGATIVE TERMINAL 
  12. INSPECT SRS WARNING LIGHT