Charging Systems: Generator: Installation
- INSTALL GENERATOR ASSEMBLY
- Provisionally install the generator with fixing bolt B.
- Provisionally install the fan belt adjusting slider with fan belt adjusting slider fixing bolts A and B, then move the generator toward the cylinder block and tighten bolt B.
Torque: 11 N*m (112 kgf*cm, 8.1 ft.*lbf)
- Install the connector and the wire harness clamp.
- Install terminal B with the nut.
Torque: 9.8 N*m (100 kgf*cm, 7.2 ft.*lbf)
- Install the terminal cap.
- INSTALL FAN AND GENERATOR V BELT (See INSTALLATION )
- ADJUST FAN AND GENERATOR V BELT (See INSTALLATION )
- INSPECT FAN AND GENERATOR V BELT (See INSTALLATION )
- INSTALL ENGINE UNDER COVER RH
- CONNECT CABLE TO NEGATIVE BATTERY
TERMINAL
Torque: 5.4 N*m (55 kgf*cm, 48 in.*lbf)