Transfer Assembly: Inspection: Inspection
WARNING: This page is about a different car, the 2011 Toyota Matrix. However, it is still accessible from the selected car via links, so may be relevant.
- INSPECT PRELOAD
- Using SST and a torque wrench, measure the preload of the backlash between the driven pinion and ring gear.
- SST: 09326-20011
Preload (at Starting)
Item Preload without SST 0.56 to 0.94 N*m (6 to 9 kgf*cm, 5 to 8 in.*lbf) with SST 0.40 to 0.67 N*m (4 to 6 kgf*cm, 4 to 5 in.*lbf) HINT:
Use a torque wrench with a fulcrum length of 130 mm (5.12 in.).
- Using SST and a torque wrench, measure the total preload.
- SST: 09326-20011
Preload (at Starting)
Item Preload without SST 0.25 to 0.44 N*m (3 to 4 kgf*cm, 3 to 3.8 in.*lbf) + driven pinion preload with SST 0.18 to 0.32 N*m (2 to 3 kgf*cm, 2 to 2.8 in.*lbf) + driven pinion preload HINT:
Use a torque wrench with a fulcrum length of 130 mm (5.12 in.).
- Using SST and a torque wrench, measure the preload of the backlash between the driven pinion and ring gear.
- INSPECT RING GEAR BACKLASH
- Using a dial indicator, check the backlash of the ring gear.
Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
Backlash
0.14 to 0.25 mm (0.00551 to 0.00984 in.)
If the backlash is not within the specification, adjust the side bearing preload or repair as necessary.
NOTE:Check at least 3 positions on the circumference of the ring gear.
- Using a dial indicator, check the backlash of the ring gear.
- INSPECT TOOTH CONTACT BETWEEN RING GEAR AND DRIVE PINION
- Coat 3 or 4 teeth at the 4 different positions on the ring gear with red lead primer.
- Rotate the ring gear to inspect the tooth pattern.
- If the tooth contact pattern is not correct, select a new transfer output shaft washer that is thicker or thinner as necessary and recheck.
- INSPECT RING GEAR RUNOUT
- Place the transfer ring gear mounting case on the V-blocks.
- Using a dial indicator, check the ring gear runout.
Maximum runout
0.06 mm (0.00236 in.)
If the ring gear runout is greater than the maximum, replace the transfer gear kit.
- INSPECT TRANSFER RING GEAR MOUNTING CASE
- Place the transfer ring gear mounting case on the V-block.
- Using a dial indicator, check the ring gear mounting case runout.
Maximum runout
0.04 mm (0.00157 in.)
If the ring gear mounting case runout is greater than the maximum, replace the ring gear mounting case.