Detailed Flow

WARNING: This page is about a different car, the 2008 Nissan Titan. However, it is still accessible from the selected car via links, so may be relevant.
NOTE: To ensure a complete and thorough diagnosis, the battery, starter and generator test segments must be done as a set from start to finish.
  1. PRELIMINARY INSPECTION

    Perform the preliminary inspection. Refer to , "INSPECTION PROCEDURE ".

    GO TO  2.

  2. DISABLE THE POWER GENERATION VOLTAGE VARIABLE CONTROL SYSTEM

    Disable the power generation voltage variable control with either of the following procedures.

    • After selecting "ENGINE" on the "SELECT SYSTEM" screen of CONSULT-III, set the "ALTERNATOR DUTY" value to 0 % by selecting "ALTERNATOR DUTY" with "Active Test". Continue "Active Test" until the end of inspection. (When the DUTY value is 0 or 100 %, the normal power generation is performed according to the characteristic of the IC regulator of the generator.)
    • Turn the ignition switch OFF, disconnect the battery current sensor connector and leave it disconnected during the course of the test.
    NOTE: Running the engine with the battery current sensor disconnected will cause DTC's (P1550-P1554) to set. After finishing the inspection, connect the battery current sensor connector and erase the self-diagnostic results history of the engine using CONSULT-III.

    GO TO  3.

  3. DIAGNOSIS WITH STARTING/CHARGING SYSTEM TESTER

    Perform the charging system test using Starting/Charging System Tester (J-44373). For details and operating instructions, refer to Technical Service Bulletin .

    Test result 

    CHARGING SYSTEM NOMAL: Charging system is normal and will also show "DIODE RIPPLE" test result.

    NO CHARGING VOLTAGE: GO TO  4.

    LOW CHARGING VOLTAGE: GO TO  12.

    HIGH CHARGING VOLTAGE: GO TO  14.

    DIODE RIPPLE NORMAL: Diode ripple is OK and will also show "CHARGING VOLTAGE" test result.

    EXCESS RIPPLE DETECTED: Replace the generator. Perform "DIODE RIPPLE" test again using Starting/Charging System Tester (J-44373) to confirm repair.

    DIODE RIPPLE NOT DETECTED: GO TO  4.

  4. INSPECTION WITH CHARGE WARNING LAMP (IGNITION SWITCH IS ON)

    Turn the ignition switch ON.

    Does the charge warning lamp illuminate? 

    Yes: GO TO  6.

    No: GO TO  5.

  5. TERMINAL "2" (OPEN) CIRCUIT INSPECTION

    Check terminal "2" circuit for open circuits. Refer to , "DIAGNOSIS PROCEDURE ".

    Is the terminal "2" circuit normal? 

    Yes: Replace generator.

    No: Repair as needed.

  6. INSPECTION WITH CHARGE WARNING LAMP (IDLING)

    Start the engine and run it at idle.

    Does the charge warning lamp turn OFF? 

    Yes: GO TO  9.

    No: GO TO  7.

  7. TERMINAL "2"(SHORT) CIRCUIT INSPECTION

    Check terminal "2" circuit for short to ground. Refer to , "DIAGNOSIS PROCEDURE ".

    Is the terminal "2" circuit normal? 

    Yes: GO TO  8.

    No: Repair as needed.

  8. TERMINAL "3" CIRCUIT INSPECTION

    Check terminal "3" circuit. Refer to , "DIAGNOSIS PROCEDURE ".

    Is the terminal "3" circuit normal? 

    Yes: GO TO  10.

    No: Repair as needed.

  9. INSPECTION WITH CHARGE WARNING LAMP (ENGINE AT 3,000 RPM)

    Increase and maintain the engine speed at 3,000 rpm.

    Does the charge warning lamp remain off? 

    Yes: GO TO  11.

    No: GO TO  10.

  10. INSPECTION OF GENERATOR PULLEY

    Check generator pulley.

    Is generator pulley normal? 

    Yes: Replace generator. Refer to , "REMOVAL AND INSTALLATION ".

    No: Repair as needed.

  11. TERMINAL "1" CIRCUIT INSPECTION

    Check terminal "1"" circuit. Refer to , "DIAGNOSIS PROCEDURE ".

    Is terminal "1" circuit normal? 

    Yes: Replace generator. Refer to , "REMOVAL AND INSTALLATION ".

    No: Repair as needed.

  12. TERMINAL "1" CIRCUIT INSPECTION

    Check terminal "1" circuit. Refer to , "DIAGNOSIS PROCEDURE ".

    Is terminal "1" circuit normal? 

    Yes: GO TO  13.

    No: Repair as needed.

  13. INSPECTION OF GENERATOR PULLEY

    Check generator pulley.

    Is generator pulley normal? 

    Yes: Replace generator. Refer to , "REMOVAL AND INSTALLATION ".

    No: Repair as needed.

  14. TERMINAL "3" CIRCUIT INSPECTION

    Check terminal "3" circuit. Refer to , "DIAGNOSIS PROCEDURE ".

    Is the terminal "3" circuit normal? 

    Yes: Replace generator. Refer to , "REMOVAL AND INSTALLATION ".

    No: Repair as needed.