Work Procedure

  1. PRECONDITIONING 

    Check that the engine is cold [coolant temperature: 50 deg. C (122 deg. F) or less].

    Is the engine cold?

    YES

    GO TO 2.

    NO

    Park the vehicle at a cold place and cool down the engine. And then, GO TO 2.

  2. INITIALIZING A LEARNING VALUE 

    SYMBOL With CONSULT

    1. Start the engine and let it idle at least 10 seconds.
    2. On CONSULT screen, select "ENGINE" >> "Active Test" >> "WASTEGATE ACTUATOR".
    3. Operate the actuator from the fully closed position to the fully open position and check that actual value is within the range of (- 0.00052) - (+ 0.00052) m when the target value is set at 0 m.

    YES

    END