Ignition Signal Check for Display Control Unit
WARNING: This page is about a different car, the 2005 Nissan Quest. However, it is still accessible from the selected car via links, so may be relevant.
- CHECK IGNITION SIGNAL
- Disconnect display control unit connector M94.
- Turn ignition switch ON.
- Check voltage between display control unit harness connector M94 terminal 12 (G) and ground.
Courtesy of NISSAN MOTOR CO., U.S.A.
Battery voltage should exist.
OK or NG
- OK: Replace display control unit. Refer to "REMOVAL AND INSTALLATION OF DISPLAY CONTROL UNIT ".
- NG: Check harness for open or short between display control unit and fuse.