Inspection Procedure

  1. CHECK BATTERY TERMINALS CONNECTION 

    Check if battery terminals are clean and tight.

    Is the inspection result normal?

    YES

    GO TO 2.

    NO

    Repair battery terminals connection.

  2. CHECK FUSE 

    Check that the following fuses and fusible link are not blown are not blown:

    Unit

    Power source (Power supply terminals)

    Fuse or Fusible Link No. or Letter

    Capacity

    Generator

    Battery (terminal 3)

    26

    10 A

    Battery (terminal 1)

    A

    140 A (VQ40DE)

    250 A (VK56VD)

    Combination meter

    Ignition switch ON (terminal 2)

    12

    10 A

    Is the fuse or fusible link blown?

    YES

    Replace the blown fuse or fusible link after repairing the affected circuit.

    NO

    GO TO 3.

  3. CHECK GENERATOR GROUND TERMINAL CONNECTION 

    Verify connector is clean and tight.

    Is the inspection result normal?

    YES

    GO TO 4.

    NO

    Repair connection.

  4. CHECK DRIVE BELT TENSION 

    Check drive belt tension. Refer to Checking Drive Belts (VQ40DE) or Checking (VK56VD).

    Is the inspection result normal?

    YES

    Inspection End.

    NO

    Repair as needed.